Applying for a drought permit
Make sure you’re ready to apply
You must apply to Natural Resources Wales for a drought permit for a site (such as the abstraction point) in Wales. Send your application to the Environment Agency if the site is in England.
Drought permits are valid for up to 6 months and can be extended for a further 6 months.
Before applying for a drought permit you should:
- check that you’re eligible to apply
- check that your drought plan supports your application – you should provide a reason for your application if it doesn’t
- carry out the measures to reduce demand for water set out in your drought plan – you should explain why if you haven’t carried them out
- write an environmental report
When you’re preparing your application you must contact:
- the relevant navigation authority for its advice on whether consent is needed - you may need consent if your application is likely to affect inland navigation
- the Water Resources Planning team in Natural Resources Wales if you’re applying to use a permit in Wales (e-mail WREPP@cyfoethnaturiolcymru.gov.uk)
- the Environment Agency if the permit could also affect England
- Natural Resources Wales (and National Parks authorities, if relevant) if your application is likely to affect a statutory designated site - such as a Habitats Directive site, Ramsar site or site of special scientific interest (SSSI). You will need to also contact Natural England of affects a designated site in England.
If you need a navigation authority’s consent
Your application will be refused by Natural Resources Wales if you need consent and the navigation authority doesn’t give it. You can apply for a drought order as an alternative if this happens.
Send any written consent from the navigation authority with your application. If you don’t need consent from a navigation authority, you must say so on your application form.
Check if you need other consents
You may also need to apply for other consents that the drought permit doesn’t cover, such as:
- land drainage consent
- an environmental permit
- planning permission
You should make sure you get any necessary consents as soon as possible, to prevent delays in processing your permit application.
Pre-application
As part of the drought planning process your drought permit application should be as ‘application ready’ as possible ahead of time. Each drought situation is different and there will be elements that you cannot prepare ahead of time. During an escalating drought situation it is important to liaise with Natural Resources Wales ahead of submitting a formal application. You should complete the following preparatory work for these discussions:
- review proposals in your drought plan
- ensure you have up-to-date data and request data where required
- undertake further monitoring or assessment (if required) to complete environmental report for the permit application
- update environmental report with an environmental assessment of the drought permit proposal
Should you submit a formal drought permit application Natural Resources Wales can also recover costs incurred at the pre-application stage.
What to include in your application
Your application must include:
- a draft copy of the permit
- a description of how you’ll use the permit
- a map clearly showing where you’ll use the permit
- an explanation of why you need the permit
Your explanation of why you need the permit must set out:
- evidence of an Exceptional Shortage of Rain (ESoR) – further detail on what to present as part of your ESoR case is available in the Water Company Drought Plan Guidance.
- the effects of the current water shortage
- how many people are affected by the shortage
- daily demand on the affected water source
- alternatives to drought permits that you’ve considered and why you’ve rejected them
- what could happen if you don’t get a drought permit
- what you’ve done so far to reduce demand and conserve supplies
- what you’ve done to comply with any relevant water resource management arrangements
- any operational changes you could make to avoid future drought-related problems
Your application must include:
- your environmental report
- a copy of the notices and advertisements relating to your application
- a description of your arrangements for the public inspection of the application
- a copy of any existing abstraction licence you hold - plus a copy of any statutory instrument or local act connected to it or to a discharge permitted by the drought permit
- any written consent you’ve had from the navigation authority
- details of the water quality for proposed new sources of water
- comments from anyone you’ve consulted about the application
- details of any objections you’ve already received or agreements you’ve reached with objectors
You must provide details of your plans for dealing with water shortages in both:
- the area covered by the permit
- the wider supply area (or the Natural Resources Wales area)
Also include information on timings, publicity activities and how you’ll work with any interested people or organisations.
Provide extra information about statutory designated sites
If your permit is likely to affect a statutory designated site you must provide enough information with your application for an environmental assessment to be made. Designated sites include Ramsar sites, special protection areas (SPAs), special areas of conservation (SACs), sites of special scientific interest (SSSIs), local nature reserves (LNRs), national nature reserves (NNRs) and marine conservation areas (MCAs).
It’s usually more appropriate to apply for a drought order than a drought permit if a Habitats Directive site is likely to be affected. You must show you’ve investigated all other options for public water supply before applying for a permit that’s likely to damage a Habitats Directive site (or if you can’t prove it won’t damage one).
You can only get a permit that affects a Habitats Directive site if there’s a reason of overriding public interest. You’ll also have to agree on any compensation needed before the permit is issued. To find out more download the guidance on overriding public interest.
You must also account for any changes to process or procedure as a result of the UK leaving the EU, for more information read about the changes to the Habitats Regulations 2017.
You should identify whether your application is likely to affect a Habitats Directive site in your drought plan.
Submit your application
You must send your application to the Natural Resources Wales Receipt Centre. You should do this by letter or e-mail.
You should:
- provide 2 complete sets of documents if you’re sending a paper submission
- send any electronic documents in Microsoft Office, PDF or an equivalent format
- send any confidential or sensitive information separately, using encryption if necessary
- check that Natural Resources Wales has received your application
Tell others about your application
You must send written notice of your application to any organisations likely to be affected by it. This will usually be:
- local authorities responsible for areas affected by the permit
- local authorities and internal drainage boards with water sources in areas affected by the permit
- other abstractors and water companies operating in areas affected by the permit
- any organisations protected by a statutory requirement (such as for compensation water) that the permit suspends or modifies
- navigation authorities responsible for any watercourse affected by the permit
Your notice must:
- state the effects of the permit
- identify the land the application relates to (if the permit authorises the occupation and use of land)
- state that all relevant maps or plans can be inspected free of charge for a period of 7 days from the date the notice is served
- state that objections to your application should be made to Natural Resources Wales within 7 days of the notice being served
Any objections should be sent to the permit receipt centre at Natural Resources Wales.
Permit receipt centre
Natural Resources Wales
Cambria House
29 Newport Road
Cardiff
CF24 0TP
E-mail: permitreceiptcentre@naturalresourceswales.gov.uk
You should also consider:
- timing your application so people aren’t prevented from raising their objections (such as public holidays may give them fewer days to respond)
- using the words ‘drought permit’ in both the title and text of your notice
- including grid references in your notice
- including details of any practical measures you’ve taken or will take to deal with the effects of the drought permit
Advertise your application
You must advertise your drought permit application in one or more local newspapers circulating in the area affected by the permit. You must also advertise it in the London Gazette.
London Gazette
PO Box 3584
Norwich
NR7 7WD
Telephone: 020 200 2434
E-mail: London@thegazette.co.uk
To avoid delays you can use regional daily papers instead of weekly ones. Free newspapers often have limited circulation, so you should only advertise in these if no other local newspapers circulate in the area.
If the drought permit affects Wales, you must publish your advertisements bilingually. If your company has a Welsh language scheme, you should follow its requirements.
You must make a complete copy of your drought permit application available for inspection by anyone for 7 days from the date it was advertised. You must not charge anyone to inspect it. Make it available at each of the following places:
- an appropriate place (such as a local Post Office), no more than 8km by road (or as near as possible in remote areas) from either the point of abstraction or the point of compensation discharge
- your head office and your office most local to the relevant area
- the Natural Resources Wales local office
Please check with Natural Resources Wales, this process may change if there are restrictions on travel.
Get a decision on your application
Withdraw your application
Call Natural Resources Wales as soon as possible if you want to withdraw a drought permit application. You should also:
- send Natural Resources Wales written confirmation of your decision to withdraw your application
- send out a press release about your decision to withdraw your application
- tell anyone who objected to your application that you’re withdrawing it
Decision on your application
Once your application has been received you’ll usually receive Natural Resources Wales’ decision within:
- 12 calendar days of the date of your last advertisement, if no objections are received or all objections are resolved and you identified your permit application in your drought plan
- 7 calendar days of the receipt of a hearing report if a hearing takes place
You’ll receive an email and letter containing:
- a written report on your application
- a hearing report if a hearing takes place
- a drought permit if one is granted
To get a decision quickly, you should:
- provide proof that you’ve published your application - send this to Natural Resources Wales as soon as possible
- respond promptly to any questions from Natural Resources Wales
- provide any other information that Natural Resources Wales asks for - send this by email and, if asked for, as a letter
- show that the drought permit is identified in your drought plan and that any objections have been resolved
What to do if there’s a hearing
You’ll get a letter from Natural Resources Wales after you’ve submitted your application.
The letter will tell you:
- the process if there’s a hearing
- the documents you’ll need to provide for the hearing
Resolve objections
Natural Resources Wales will send you a copy of each objection they receive. You may then resolve issues with the objectors to reach an agreement and avoid a hearing.
Before negotiating with objectors, send them a statement setting out your reasons for making the application. This should include:
- a list of any documents, maps or plans that you’d rely on at a hearing, with advice on where these can be inspected and copied
- your application documents
- any other documents from relevant statutory bodies
When a hearing is needed
A hearing will take place if:
- a person or organisation makes a reasonable objection with clearly stated grounds
- no agreement is reached between you and the objector
- the objection isn’t withdrawn
- Natural Resources Wales decide that the objection can’t be dealt with by compensation instead
Object to the decision to hold a hearing
You can’t appeal against the decision of Natural Resources Wales to hold a hearing. However, you can withdraw your drought permit application and apply for a drought order from the Welsh ministers instead.
If there’s an urgent need for a drought permit the Welsh ministers may decide that a hearing shouldn’t go ahead. You should send a full supporting case to Natural Resources Wales proving there’s an urgent need for a permit if you wish to request this.
Who will run the hearing
Natural Resources Wales will appoint one of the following to run the hearing:
- an inspector from the Planning Inspectorate (visit the website of the Planning Inspectorate Wales)
- a member of its own staff
- a suitable third party
Get a date for your hearing
Natural Resources Wales will arrange a suitable venue for a hearing. A hearing can take place any time after the 7-day limit for lodging objections, but it should take place relatively quickly.
Natural Resources Wales will notify all parties of the date, time and venue for the hearing. They will usually provide 7 days’ notice, though this may be shortened in more urgent cases. If Natural Resources Wales considers the application to be of enough public interest, it will issue a press release or ask you to provide publicity.
Send a statement of fact
You should agree the factual basis of your case with any objectors before the hearing takes place. Set out the factual basis in a document (this is known as a ‘statement of fact’) and send it to the person running the hearing. This is to prevent disputes during the hearing on factual matters (such as rainfall data).
You should also tell the person running the hearing about anything that occurred after you sent your application that needs to be considered during the hearing (such as a change in rainfall, environmental issues or any other new developments).
What happens at the hearing
The person running the hearing will decide on its structure. However, the procedure is usually as follows:
- you’re asked to speak first
- objectors are then asked to speak – they may give evidence or ask questions (questions will normally be channelled through the person running the hearing, who may also ask questions of their own)
- you’re given an opportunity to make closing comments
The person running the hearing may make an informal site visit before the hearing to find out more about the affected area.
Fees
Natural Resources Wales will recover all the costs of the hearing, including any fees for the venue. This will happen after a decision has been made on your drought permit application. The Planning Inspectorate will also charge a fee for the inspector’s time and any travel and subsistence costs incurred.
After the hearing
After the hearing, the person who ran it will submit a report to Natural Resources Wales.
The report will set out:
- who objected at the hearing and what they said
- your response to each objection, including answers to any questions
- the decisions of the person who ran the hearing, including findings, suggested modifications and conclusions
The report will not make a recommendation on how the application should be decided. Natural Resources Wales aim to make a decision within 7 calendar days of the receipt of the hearing report, though this period can be longer or shorter.
After you’ve received your drought permit
Advertise a successful application
You must advertise a successful application in:
- the London Gazette
- the same local newspaper where you advertised your application
Your advertisement must specify where the permit can be inspected (these should be the same places where you made your application available for inspection).
Pay compensation
As the applicant you’re liable to pay compensation for any loss or damage caused by a drought permit. Any of the following can claim compensation:
- the owners of the water source associated with the drought permit
- anyone with an interest in that source (such as fishing clubs, navigation clubs, biodiversity groups)
Anyone applying for compensation must send you their claim within 6 months of the expiry of the permit.
You should refer any disputes about compensation to the Upper Tribunal (Lands Chamber). For more information visit the website of the Upper Tribunal. Disputes can’t be dealt with at hearings.
Pay back costs
You may have to pay Natural Resources Wales for the cost of:
- any monitoring carried out on your behalf
- local inquiries or hearings
- processing your application (such as staff time, overheads and equipment – including at pre-application stage)
- pre-agreed mitigation or restoration activities
Natural Resources Wales will:
- inform you when we consider the pre-application stage has formally begun (i.e. from when we can recover costs should a formal application be made)
- issue a letter of intent to recover costs upon submission of a formal application
- record the time it gives to each individual permit, to allow charges to be calculated
- provide an itemised invoice and covering letter within 12 months of expiry of the drought permit, to make sure the cost recovery process is transparent
Extend your drought permit
You can apply to extend an existing drought permit for up to 6 months. You must contact Natural Resources Wales at least 28 days before the existing permit expires if you plan to do this. Include all supporting materials with your application, including any new evidence, including:
- a continued exceptional rainfall deficit
- monitoring the effects of the existing drought permit
You’ll receive a decision within:
- 12 calendar days if there’s no hearing
- 7 calendar days of the receipt of the hearing report if there’s a hearing
Natural Resources Wales will consider any objection made against the original application for a permit if the objection is now more relevant due to a change in circumstances.
Drought permits can’t be in force for more than 12 months. You must make a new application to renew a permit after this time.
Amend your drought permit
You’ll need to send a full application to amend a drought permit. However Natural Resources Wales can make minor amendments to a drought permit, such as to change the precise wording of the permit. You should contact Natural Resources Wales for advice on this.
Cancel your drought permit
You can stop using a drought permit at any time, as long as this doesn’t go against the permit’s conditions or restrictions. Write to Natural Resources Wales to cancel your permit. Send out a press release to tell the public that your permit has been cancelled.
Your permit could be cancelled if you don’t follow its rules. You’ll get a written warning from Natural Resources Wales before it’s cancelled.
Offences
You must not take, use or discharge water unless you’re authorised to.
You must:
- build or maintain any apparatus for measuring water flow that’s required by a drought permit - make sure you have the relevant consent to do this (such as land drainage consent or an impoundment licence)
- allow authorised people to inspect the water system or examine or take copies of records connected to it
You could be fined if you can’t show that you took all reasonable precautions and did everything you could to avoid committing these offences.
It’s also an offence to knowingly or recklessly make false statements to obtain a drought permit.